All persons subject to the
requirements of Illinois State Law should plan and conduct their excavation
work consistent with reasonable business practices.
Conditions may exist making it unreasonable to request
that locations be marked within the normal 48 hour (two-working days)
notice. It is unreasonable to request owners and operators of
underground utility facilities to locate all of their facilities in an
affected area upon short notice in advance of a large or extensive
non-emergency project, or to request extensive locates in excess of a
reasonable excavation or demolition work schedule, or to request locates
under conditions where a repeat request is likely to be made because of the
passage of time or adverse job conditions.
It is the policy of JULIE to limit the number of addresses
on each normal locate request. Excavators are limited to 10 (ten)
addresses, on the same street within the same "hundred" block, per dig
number.