Once received, locate requests are processed through the JULIE computer system.  The geographic information contained in the request determines which JULIE member companies have facilities in or near the proposed excavation area.  

These members will be notified by JULIE and dispatch company representatives within forty‑eight hours (2 business days) beginning at 8 a.m. and ending at 4 p.m. (exclusive of Saturdays, Sundays, and holidays recognized by the State‑Wide One‑Call Notice System or the municipal one‑call notice system). All requests for locates received after 4 p.m. will be processed as if received at 8 a.m. the next business day.  White-lining your project can expedite the process saving time and money.

Wait The Required Amount of Time
You may not begin your excavation before the dig start time of your ticket, even if all utilities have been marked.  However, you must begin your project within 14 days of your contact with JULIE.